11/05/2026
The Garage door is installed! Water Heater has been installed. Low voltage trim out, lighting, fixtures, bathroom shower glass enclosures, closet shelving’s installed.
Rough clean next. Front of house brick to be installed this week! Appliances to be delivered end of this week! Drywall punch list to be done!
A few delays in October has pushed the Pavers, landscaping, irrigation, railing to the 3rd week of November 16th-23rd!