"Exciting milestone! One of our single-family construction project is in the final inspection phase, bringing us one step closer to the Certificate of Occupancy. 🏡✅ This week, we focused on ensuring all electrical, HVAC, and plumbing systems are fully operational. Almost there!. This final phase of the project requires passing all inspections to obtain the CO (Certificate of Occupancy) issued by the County and is an intense process where at least 8 individual inspections are required ensuring the property is safe for living and meet all the County's building codes.
Roof Final Inspection: PASS
Tree Inspection: PASS
Drainage As Built Inspection: PASS
ROW Grade Final Inspection: PASS
ROW Final Inspection: PASS
CCU Vacuum Sewer Final-Pending
Blower Door Certification/Test-Pending
Building Final-Pending