🚨🚨 ALERT! NIPSCO JUST RELEASED THE RESTORATION TIMELINE NORTHWEST INDIANA HAS BEEN WAITING FOR. 🚨🚨
NIPSCO has finally provided its first system-wide estimate for when power will be restored following the largest and most destructive outage event in company history.
Approximately 90% of impacted customers are expected to have power restored by 11:59 p.m. Tuesday, August 18.
NIPSCO expects restoration to reach 100% of customers by 11:59 p.m. Friday, August 21.
The big question everyone in Portage and the rest of Northwest Indiana is asking is whether their town will be Tuesday, Friday, or somewhere in between.
Unfortunately, NIPSCO does NOT have that answer yet.
Community-specific restoration estimates are currently being developed and are expected to be released Sunday evening, August 16.
Damage varies dramatically throughout Northwest Indiana, which means some communities and neighborhoods will get power back considerably sooner than others.
Crews are also continuing to discover additional damage, so these estimates could change as repairs progress.
Another important update is that NIPSCO's automated outage notification system is currently unavailable because of the unprecedented volume of outages. Customers should not expect the normal text or email restoration alerts right now.
For everyone in Portage, Chesterton, Valparaiso, Hobart, Crown Point, Merrillville, Gary, Michigan City and throughout Northwest Indiana, Sunday evening is now the next major update to watch.
Until then, people ARE getting power back, crews ARE making progress, and thousands of workers continue working through an absolutely historic amount of damage.
Thank you to every lineman, contractor, first responder and public works crew that has been grinding through this disaster.
If your power comes back, PLEASE comment with your town, street and approximately what time it was restored so the rest of Northwest Indiana can see where progress is happening.
Share this everywhere. People need to know what NIPSCO just announced.