06/03/2023
Weeks 8 - 10
We visited at the weekend to check on progress and keep on top of any snags identified to not delay the completion.
- Kitchen is now 90% complete
- Both attic rooms are now insulated and plastered
- Hallway areas from ground to attic are plastered or prepped ready for remaining plastering
- Skirting and architraves fitted to all areas
- Internal doors have been hung
- Tiling to all en-suites complete
- Sanitary wear is being installed
- Ground floor service cupboard constructed
- Scaffold to front and rear erected
- Window and door installations externally have begun
- Heating system is live, boiler and cylinder installed and all rads fitted
- All floor covering choices selected, vinyl for kitchen and en-suites. Carpets for communal and bedroom areas