VILLA VIRTUOSO Investor Update – January 2023
Happy New Year everyone, we’re incredibly grateful to be sharing our January 2023 progress update with you, our VIRTUOSO Investor Family & Community.
Now that we’re well into winter, the Roof is on and the temporary heat system is keeping our building warm and dry the drywall is progressing well at about 60% complete, with insulation at about 80% complete, Windows and Doors are installed in preparation for interior paint and finishes. Siding is about 50% complete and we’re in good shape as we work through the rainy/snowy season.
We’re in full sub trade mode now with Electrical, Mechanical, Plumbing, Siding, Elevator and other contractors continuing to progress. The installation of Drywall is a major milestone that our On-Site Construction Management Team deserves massive credit for.
Huge Shout out to our On-Site VCV Project Manager Michael Genovese and our Construction Manager (CM) Sargent Construction Ltd. http://www.sargentconstruction.ca/pastjobs.html led by Lyall Sargent, a welcome addition to the VIRTUOSO Team.
Progress Highlights:
Virtuoso Venture Inc. employees Justin and Bratzo assembling scaffolding for the siding crew during the big snowfall in December.
Siding mostly complete on the West wall.
Nick Kent completing stairwell Shear Walls and other framing.
All interior bedroom and bathroom walls as well as party walls are insulated for soundproofing.
Drywall progressing on the 3rd, 4th and 5th floors.
Temporary Heat.
Amenities level ready for drywall mid January.
Throwback to summer, the ownership/management team hard at work 😊
From left to right: Rick Genovese, Michael Genovese, Justin Genovese, Robert Klein.